Report Activity Progress
- The progress will be reported based on the Reporting date. If you need to change the Reporting date, please check Change Reporting Date.
- To add activity progress, please enter the progress percentage as follows:
- To mark an activity as finished:
Report Root Cause of Delay by pressing on Report Cause of Delay:
- If you need to add a specific cause of delay that is not available in the default menu, please contact the support team by emailing support@reconstructinc.com.
Comments
0 comments