Learn how to change the timeline date of a point cloud with this simple guide. We'll walk you through the necessary steps to adjust the timeline date in the Data Manager. There are several types of dates associated with each point cloud:
- Creation date: the date a user processed images to create the point cloud
- Capture date: the date range of the earliest and latest image dates in the point cloud
- Timeline date: the date that will be displayed in the timeline in Reconstruct Viewer
Step 1: Access the Point Clouds Tab
First, go to the Data Manager in your project and navigate to the Point Clouds tab.
Step 2: Show the "Timeline Date" Column
If the "Timeline Date" column is hidden, click on the gear icon to customize the table view and enable the "Timeline Date" column.
Step 3: Click the Timeline Date of the Point Cloud
Find the point cloud you want to adjust the timeline date for and click on its current timeline date.
Step 4: Select a New Date
Choose a new date from the calendar or select one of the preset dates in blue. Click "Save" to apply the new timeline date to the point cloud.