As an alternative to reporting progress and details of activities and task completion or delays using the Reporter App, you may also report on your schedule using the Progress View of your schedule while in Edit mode.
While in Edit mode, simply go to the Progress View of your schedule, and using the filters provided, select a time frame or day for which you want to report. Input on the corresponding activity or task its progress, crew size, work hours, and any Root cause that made the activity or task deviate from the plan. (Note that progress reported under tasks will automatically update the total overall progress of its parent activity:
Once reported, Publish your schedule to reflect the changes of progress.
For more information on how to use the filters or a combination of them, see our section on Schedule Modes (Gantt & Progress).